Loveland Project Framing Tour: Exterior

IMG_4580.JPG

Today we are trying out something new, a video tour of our current project. This video in particular is of the exterior framing. The goal is is give our readers an idea of how the home is shaping up and to also start getting videos out there. It’s all a work in progress! Next week we hope to have a second video of the interior spaces posted.

*This video takes a moment to start playing from the time you press play.

Sprouting Up

Aaahh, spring has arrived in Colorado…or at least it seems that way on a bi-weekly basis. One week sunny and hot, the next cold and wet.

As promised, in the previous post a look into how the framing has been going. We have brought on, J & D Builders from Greeley to help us out, and we are really enjoying working with them.

IMG_4559e

Profile view. The Kitchen area has trusses on. The garage is being sheathed for the second floor.

IMG_4488

Tilting up walls. These guys have had no problem working with our double wall framing system.

IMG_4542

Looking out the Dinning room window, that tiny person was placed there for scale. The homeowners wanted big windows to really capture the view they have of the buttes and Horsetooth Rock from the North side of their home.

IMG_4545

Jason and Bryan standing in the Kitchen.

IMG_4550

Looking out from the Kitchen into the rest of the first level. The “tiny person for scale” is standing in the Master Bedroom. The beam is situated over the Living Room.

IMG_4552

Here our scale model is standing under the beam and in front of her is the wash room and access to the garage. There are high ceilings throughout. The beams and columns for this project are Beetle Kill Pine, milled from The Forks Lumber Mill, whom we used for the Nederland Home.

IMG_4539

Here’s a look into the wall cavity. Soon we will be dense packing a whole semi load of cellulose into these cavities. One the ground is our vapor barrier. Just as on a roof, we must maintain a dry environment for the durability of our materials and the house as a whole.

IMG_4556

Scale Model standing in the Garage. Above the garage will be bedrooms.

IMG_4533

Here’s a look at some amazing custom made brackets we had done for the home from Charles Lefkowitz at, Sculpture and Functional Metal Work. We will have an upcoming post with more photos of the brackets we are using.

IMG_4501

IMG_4536

There last two photos are of the column brackets, one from the side, and one from the front. These brackets are giving structural stability and a very modern and industrial look to the home.

 

That Brindle Look

Have you missed us? We’ve been busy but have some exciting update posts on the way to show just how things are progressing!

IMG_4398e

We’ve poured the concrete floor, and remaining walls on our Loveland site. We had some really strong winds Tuesday while we poured the walls, making for a lot of fun with the pump truck and hose. The following day was much calmer and hotter, and we started bright and early. The pour went smoothly, thanks in part to great team work from everyone and having a good pump operator…and a tiny person to keep everyone  in check!

IMG_4448e

Hammer-Wielding Tiny Girl Boss

The slab is going to be stained, and to give it a nice look, we’ve burnished it. The slab is also fitted for radiant floor heating.

IMG_4386IMG_4393IMG_4398eIMG_4404IMG_4406IMG_4412

Quinn (above) stripping forms where the outdoor fireplace will be. The concrete was poured in several locations with the board formed look, giving it a rustic and also modern feel. 

IMG_4418IMG_4420IMG_4426IMG_4424IMG_4440IMG_4452IMG_4456

Later in the afternoon, we began stripping the foundation forms and Jason started making saw cuts the following day.

IMG_4475IMG_4480

In the next post, we will be showing off how the framing is going. We’ve had a few stall days due to rain (and snow) but it’s moving along and we can’t wait to post about it!