Once the walls were poured, we got right to work getting the floor ready to be poured.
Steps that had to be taken before concrete could be laid were: trench for in-slab plumbing, trench for drainage and radon mitigation, backfill, compact, install steel posts and beams, move in and level gravel, lay out foam, lay out plastic, install rebar mesh, install heat loops, and add chairs for mesh.
Have any thoughts or questions? Let us know in the comments!